High Volts Wind Farm

Project Info

  • Category

    Driven Pile

Description


Driven Piles and Grout Consolidation

Client: Powergen Renewables Ltd
Works Contractor: MG Piling

MG Piling were responsible for the design and construction of piles and grout consolidation of the foundations to wind turbines on the remote site.

Grout was injected to a depth of 20 metres to consolidate potentially unstable coal seams on the Durham site to enable driven piles to terminate on rock overlying this coal.

A relatively shallow depth to rock on the Hartlepool site resulted in a combination of driven piles and rock-socketed piles being used to provide the compression and tension requirements of the foundation base.